Oran Pre-Cast proposed a precast concrete frame as a viable alternative to the cast in situ RC flat slab design
CLIENT | Grangegorman Development Agency |
---|---|
MAIN CONTRACTOR | SISK |
ARCHITECT | Moloney O'Beirne |
ENGINEER | Horgan Lynch |
PRECAST VALUE | €1.1m |
ONSITE DURATION | 10 weeks |
The building is framed around 2 irregular shaped internal courtyards, intersected at an angle by a 3 storey administration block.
This geometry resulted in a high number of bespoke precast elements, with very little repetition between members. Rectangular, half-filled composite, spine and edge beams were all used as required.
Points of interest include:
-
Cantilevering floor slabs
-
Feature 8m long stairs
-
Beams of over 14m in length
-
Lattice floor with circular rooflight openings
-
Service openings provided in downstand beams and
-
Over 400 individual production drawings
The prestressed hollowcore flooring allowed for greater spans than a similar RC slab. This reduced both the number of supporting columns required, and the overall dead load onto the foundations.