Oran Pre-Cast worked closely with the main contractor to provide precast solutions to the reinforced concrete frame
CLIENT | Gallico Developments |
---|---|
MAIN CONTRACTOR | JJ Rhatigan |
ARCHITECT | Murray O Laoire Architects |
ENGINEER | O'Connor Sutton Cronin |
PRECAST VALUE | €4.9m |
ONSITE DURATION | 72 weeks |
This large mixed use development is spread over an 8 acre site in the centre of Athlone town. The reduction in on-site works associated with precast concrete construction, in-terms of both material and labour, was of immense value on this congested town centre site.
Oran Precast supplied and delivered directly to the main contractor.