Oran Precast worked closely with the consulting engineer and main contractor to provide a total precast solution for this project

MAIN CONTRACTOR Burkeway
ARCHITECT OKM
ENGINEER HGL O'Connor
PRECAST VALUE €2m
ONSITE DURATION 20 weeks

This development consists of retail, office and residential units over a basement carpark. The building forms the focal point of the bustling Lisbaun Industrial Estate.

Key design features included:

  • Precast column and beam structure

  • Twinwall staircores and liftshafts

  • Hollowcore flooring throughout

  • Interface connection between insitu base slab and precast frame

 

Oran Pre-Cast worked closely with the main contractor to provide precast solutions to the reinforced concrete frame

CLIENTGallico Developments
MAIN CONTRACTOR JJ Rhatigan
ARCHITECT Murray O Laoire Architects
ENGINEER O'Connor Sutton Cronin
PRECAST VALUE €4.9m
ONSITE DURATION 72 weeks

This large mixed use development is spread over an 8 acre site in the centre of Athlone town. The reduction in on-site works associated with precast concrete construction, in-terms of both material and labour, was of immense value on this congested town centre site.

Oran Precast supplied and delivered directly to the main contractor.

 

The exposed precast concrete perimeter beams play an important role in defining the external elevations of this commercial building

MAIN CONTRACTOR Purcell Construction
ARCHITECT Paul Dillon Architects
ENGINEER O'Connor Sutton Cronin
ONSITE DURATION 2 weeks

The exposed nature of the beams meant that special consideration had to be given to cast in items, such as temporary bracing sockets and lifters. The location of joints and chamfer details was also of high importance. The connection to the internal concrete slab incorporated a structural thermal break element. RIAI winner of best commercial / retail building 2011.

 

This multi-storey irregular shaped building showcases the flexibility of our precast concrete solutions
MAIN CONTRACTOR GK Developments
ARCHITECT Sean Dockery & Associates
ENGINEER HGL O'Connor
PRECAST VALUE €4.3m
ONSITE DURATION 26 weeks

Oran Pre-Cast relied on years of experience in the mixed use sector to deliver one of our most complex projects to date. The floor layout and building geometry varied greatly between the 7 levels, leading to a large number of bespoke elements and some significant transfer structures.

Our in house design team created a detailed 3-dimensional model to aid the design process. The model was invaluable when it came to designing and detailing the more complex elements and connections. The Tekla software package automatically generated production drawings of the various elements which greatly sped up the detailing process.

 

Key design features included:

  • 2no. 40 tonne transfer beams

  • Cantilevering lattice floor design

  • Bespoke downstand and cantilevering edge beams

  • Allowance for future vertical expansion

  • Exposed circular columns